NERC Requirements

North American Electric Reliability Corporation

FAC

FAC-001-4 – Facility Interconnection Requirements

Source: https://www.nerc.com/pa/Stand/Reliability%20Standards/FAC-001-4.pdf

Status: Effective January 1, 2024

Applicability: Generator Owner (GO) with fully executed Agreement to conduct a study on the reliability impact of interconnecting a third-party facility to the GO’s existing facility used to interconnect to the transmission system.

Description: Requires GOs to make facility interconnection requirements available so that entities seeking to interconnect will have necessary information.

Summary Requirements:

  • R2: Each GO shall document facility interconnection requirements and make them available upon request within 45 calendar days of full execution of an Agreement to conduct a study on the reliability impact of interconnecting a third-party facility to the GO’s existing facility used to interconnect to the transmission system.
  • M1, M4: Each GO shall have evidence (such as dated, documented facility interconnection requirements) that it met all requirements in R2 and R4, including:
  • R4.1: procedures for coordinated studies of new interconnections and their impacts on affected systems.
  • R4.2: procedures for notifying those responsible for the reliability of affected systems of new interconnections.
  • R4.3: procedures for confirming with those responsible for the reliability of affected systems that new facilities or existing facilities seeking to make a qualified change as defined by the Planning Coordinator are within a Balancing Authority Area.
  • C1.2: Retain documentation as evidence for three (3) years and if found non-compliant you must retain information regarding the non-compliance until mitigation is complete and approved or for the three (3) year period, whichever is longer.

Violation Severity Levels:

  • Lower: 45-60 calendar days
  • Moderate: 60-70 calendar days
  • High: 70-80 calendar days
  • Severe: > 80 calendar days

Look Ahead: This FAC is currently the subject of a SAR “Revisions to FAC-001-4 and FAC-002-4”.

Look Ahead Source: https://www.nerc.com/comm/RSTC_Reliability_Guidelines/Draft_Revisions_to_FAC-001-4_and_FAC-002-4_SAR.pdf

Look Ahead Description: The SAR may include additional requirements for facilities seeking interconnection, including:

  • General interconnection technical specifications and performance requirements:
  • Reference points of applicability (e.g., specifying where the interconnection requirements apply, e.g. point of interconnection)
  • Applicable voltages and frequencies (e.g., specifying the meaning of voltage and frequency for each of the following interconnection requirements (e.g., phase or instantaneous values, etc.))
  • Measurement accuracy (e.g., specifying the accuracy of steady state and transient measurement, accuracy requirements for an IBR Facility’s performance monitoring and validation)
  • Operational measurement and communication capability (e.g. specifying communication capabilities required from an IBR Facility for providing real-time operational information)
  • Control capability requirements (e.g. specifying the capability of an IBR facility to respond to external control inputs, e.g., capability to limit active power as specified by a TO)
  • Prioritization of IBR responses (e.g., specifying the priority of IBR Facility responses to TO’s interconnection requirements)
  • Isolation device (e.g., specifying the requirement for break isolation device between the TO’s network and the IBR Facility)
  • Inadvertent energization of the transmission system (e.g., specifying requirements for IBR Facility when the TO’s network is de-energized)
  • Enter service (e.g., specifying requirements for IBR Facility performance when entering service after an IBR Facility was out of operation)
  • Interconnection integrity (e.g., specifying protection from electromagnetic interference, surge-withstand performance, and interconnection switchgear)
  • Integration with TS grounding (e.g., specifying requirements for the integration of grounding scheme between an IBR Facility and TO’s network)
  • Reactive power-voltage control requirements within the continuous operation region:
  • Reactive power capability (e.g., specifying reactive power capability at the reference point of applicability)
  • Voltage and reactive power control modes (e.g. specifying voltage regulation capability by changing reactive power output, and coltage control modes during normal operation)
  • Active power and frequency response requirements:
  • Primary frequency response (e.g., specifying requirements for the primary frequency response)
  • Fast frequency response (e.g., specifying requirements for any fast frequency response, i.e., response to changes in frequency during the arresting phase of a frequency excursion to improve the frequency nadir or initial rate-of-change of frequency)
  • Active power ramp rate performance (e.g., specifying performance requirements for active power ramping. Alternatively, this requirement can be embedded in other performance requirements (e.g. Enter Service, Primary Frequency Response Requirement, etc.) as appropriate).
  • Response to transmission system abnormal conditions:
  • Voltage (e.g., specifying requirements for IBR Facility performance during and after large-signal voltage disturbances, including transient overvoltage ride-through and dynamic voltage support requirements)
  • Frequency (e.g., specifying requirements for IBR Facility performance during and after a large-signal frequency disturbance, including rate-of-change of frequency and voltage phase angle ride-through requirements)
  • Return to service after an IBR plant trip (e.g., specifying requirements for IBR Facility performance if it trips during or after a large-signal voltage or frequency disturbance)
  • Protection (defining requirements for protective functions at an IBR Facility and coordination with the TO)
  • Modeling Data (e.g., specifying requirements for IBR Facility models to be provided to TOs):
  • Verification report comparing modeled parameters against to-be-commissioned parameters
  • Model Validation report showing benchmarking between all submitted model types (Standard Library Model, Positive Sequence User-defined model, and Electromagnetic Transient (EMT)) and the real equipment as per FERC Order 2023
  • Measurement data for performance monitoring and validation (e.g., specifying measurements, data recording, and retention requirements at an IBR Facility for the purpose of performance monitoring and validation during na IBR Facility operation)
  • Test and verification requirements (e.g., specifying requirements for testing and verifying an IBR Facility’s conformity with applicable interconnection requirements during the interconnection process, at the commissioning stage, and during IBR Facility operation)
FAC-002-4 – Facility Interconnection Studies

Source: https://www.nerc.com/pa/Stand/Reliability%20Standards/FAC-002-4.pdf

Status: Effective January 1, 2024

Applicability: Generator Owner (GO) with fully executed Agreement to conduct a study on the reliability impact of interconnecting a third-party facility to the GO’s existing facility used to interconnect to the transmission system.

Description: Requires GOs to coordinate and cooperate on studies of the reliability impact of new interconnections and existing interconnections making a qualified change.

Summary Requirements:

  • R2: Each GO shall coordinate and cooperate on studies with its transmission planner or planning coordinator, including but not limited to the provision of data in R1, Parts 1.1-1.4:
  • R1.1: reliability impact of the new interconnection or existing interconnection seeking a qualified change.
  • R1.2 adherence to applicable NERC reliability standards, regional and transmission owner planning criteria and facility interconnection requirements.
  • R1.3: Steady-state, short-circuit, and dynamics studies, as necessary, to evaluate system performance under both normal and contingency conditions.
  • R1.4: Study assumptions, system performance, alternatives considered, and coordinated recommendations. Studies may be performed independently. Results shall be evaluated and coordinated by entities involved.
  • M2: Each GO shall have evidence (such as documents containing the data provided in response to the requests of the transmission planner or planning coordinator) that it met all requirements of R2.
  • R5: Each GO shall coordinate and cooperate with its transmission planner or planning coordinator on studies regarding requested interconnections to its facilities, including but not limited to the provision of data as described in R1, Parts 1.1-1.4
  • M5: Each GO shall have evidence (such as documents containing the data provided in response to the requests of the transmission planner or planning coordinator) that it met all requirements of R5.
  • C1.2: Retain documentation as evidence for three (3) years and if found non-compliant you must retain information regarding the non-compliance until mitigation is complete and approved or for the three (3) year period, whichever is longer.

Violation Severity Levels: R2

  • Lower: cooperated but failed to provide data on one of the Parts R1.1-1.4
  • Moderate: cooperated but failed to provide data on two of the Parts R1.1-1.4
  • High: cooperated but failed to provide data on three of the Parts R1.1-1.4
  • Severe: failed to cooperate

Violation Severity Levels: R5

  • Lower: cooperated but failed to provide data on one of the Parts R1.1-1.4
  • Moderate: cooperated but failed to provide data on two of the Parts R1.1-1.4
  • High: cooperated but failed to provide data on three of the Parts R1.1-1.4
  • Severe: failed to cooperate

Look Ahead: This FAC is currently the subject of a SAR “Revisions to FAC-001-4 and FAC-002-4”.

Look Ahead Source: https://www.nerc.com/comm/RSTC_Reliability_Guidelines/Draft_Revisions_to_FAC-001-4_and_FAC-002-4_SAR.pdf

Look Ahead Description: The SAR may include additional requirements for facilities seeking to make a qualified change related to physical testing or simulation-based assessment using detailed, accurate models representative of the facility and leveraging the work of the IEEE2800.2 working group.

FAC-008-5 – Facility Ratings

Content unavailable at this time

PRC

PRC-002-4 – Disturbance Monitoring and Reporting Requirements

Source: https://www.nerc.com/pa/Stand/Reliability%20Standards/PRC-002-4.pdf

Status: Effective April 1, 2024

Applicability: Each Generator Owner (GO) with gross individual nameplate rating greater than or equal to 500MVA or gross individual nameplate rating greater than or equal to 300 MVA where the gross plant/facility aggregate nameplate rating is greater than or equal to 1,000 MVA for dynamic disturbance recording (DDR) data. Each GO who has received notice from a Transmission Owner (TO) that the GO is required to maintain sequence of events recording (SER) and/or fault recording (FR) data. NB. TOs may elect which GOs to send requests based upon pre-existing availability of SER and/or FR data at buses, and must notify GOs within 90 calendar days of identifying buses for which data is lacking. TOs must re-evaluate buses every five (5) years, so it is possible GOs that have not received notice will receive one in the future.

Description: Requires GOs to maintain and supply data relevant to the analysis of disturbances.

Summary Requirements:

  • R2: Each notified GO must have SER data for circuit breaker position (open/close) for each circuit breaker it owns connected to the bus.
  • M2: Each notified GO must have evidence of SER data for circuit breaker position, which may include but is not limited to (1) documents describing the device interconnections and configurations which may include a single design standard as representative of common installations; or (2) actual data recordings; or (3) station drawings.
  • R3: Each notified GO shall have FR data to determine the following electrical quantities for each triggered FR for elements it owns directly connected to the bus:
  • R3.1: Phase-to-neutral voltage for each phase of each specified bus
  • R3.2: Each phase current and the residual or neutral current for the following elements:
  • R3.2.1: transformers that have a low-side operating voltage of 100 kV or above.
  • R3.2.2 transmission lines
  • M3: Each notified GO has evidence of FR data sufficient to determine the electrical quantities in R3, which may include but is not limited to (1) documents describing the device specifications and configurations which may include a single design standard as representative for common installations; or (2) actual data recordings or derivations; or (3) station drawings.
  • R4: Each notified GO shall have FR data that meets the following:
  • R4.1: A single record or multiple records that include (1) a pre-trigger record length of at least two cycles and a total record length of at least 30 cycles for the same trigger point, or (2) at least two cycles of the pre-trigger data, the first three cycles of the post-trigger data, and the final cycle of the fault as seen by the fault recorder
  • R4.2: A minimum recording rate of 16 samples per cycle
  • R4.3 Trigger settings for at least the following:
  • R4.3.1: Neutral (residual) overcurrent
  • R4.3.2: Phase undervoltage or overcurrent
  • M4: Each notified GO has evidence that FR data meets R4, which may include but is not limited to (1) documents describing the device specification (R4, Part 4.2) and device configuration or settings (R4, Parts 4.1 and 4.3), or (2) actual data recordings or derivations.
  • R7: Each GO shall have DDR data to determine the following electrical quantities for each element it owns for which it received notification by the TO:
  • R7.1: One phase-to-neutral, phase-to-phase, or positive sequence voltage at either the generator step-up transformer (GSU) high-side or low-side voltage level
  • R7.2: The phase current for the same phase at the same voltage corresponding to the voltage in R7.1, phase current(s) for any phase-to-phase voltages, or positive sequence current
  • R7.3 Real Power and Reactive Power flows expressed on a three-phase basis corresponding to all circuits where current measurements are required
  • R7.4: Frequency of at least one of the voltages in R7.1
  • M7: Each GO has evidence of DDR data to determine electrical quantities in R7 which may include but is not limited to (1) documents describing the device specifications and configurations, which may include a single design standard as representative for common installations or (2) actual data recordings or deviations, or (3) station drawings.
  • R8: Each GO responsible for DDR data shall have continuous data recording and storage. If the equipment was installed prior to the effective date of PRC-002-2 (US: July 1, 2016) and is not capable of continuous recording, triggered records must meet the following:
  • R8.1: Triggered record lengths of at least three (3) minutes
  • R8.2: At least one of the following three triggers:
  • Off nominal frequency trigger set at:
  • Rate of change of frequency trigger set at:
  • Undervoltage trigger set no lower than 85 percent of normal operating voltage for a duration of 5 seconds
  • M8: Each GO has dated evidence of data recordings and storage in accordance with R8. Evidence may include but is not limited to (1) documents describing the device specifications and configurations, which may include a single design standard as representative for common installations, or (2) actual data recordings.
  • R9: Each GO responsible for DDR data in R5 shall have DDR data that meets the following:
  • R9.1: Input sampling rate of at least 960 samples per second
  • R9.2: Output recording rate of electrical quantities of at least 30 times per second
  • M9: Each GO has evidence that DDR data meets R9. Evidence may include but is not limited to (1) documents describing the device specification, device configuration, or settings (R9.1, R9.2) or (2) actual data recordings (R9.2).
  • R10: Each GO shall time synchronize all SER and FR data for the buses identified in R1 and DDR data for the elements identified in R5 to meet the following:
  • R10.1: Synchronization to UTC with or without a local time offset
  • R10.2: Synchronized device clock accuracy within 2ms of UTC
  • M10: Each GO has evidence of time synchronization described in R10. Evidence may include but is not limited to (1) documents describing the device specification, configuration or settings, or (2) time synchronization indication or status, or (3) station drawings.
  • R11: Each GO shall provide upon request all SER and FR data for the buses identified in R1 and DDR data for the elements identified in R5 to the Reliability Coordinator, Regional Entity or NERC in accordance with the following:
  • R11.1: Data will be retrievable for the period of 10 calendar days, inclusive of the day the data was recorded
  • R11.2: Data subject to Part 11.1 will be provided within 30 calendar days of a request unless an extension is granted by the requestor
  • R11.3: SER data will be provided in ASCII Comma Separated Value (CSV) format following Attachment 2
  • R11.4: FR and DDR data will be provided in electronic files that are formatted in conformance with C37.111, (IEEE Standard Common Format for Transient Data Exchange (COMTRADE), revision C37.111-1999 or later
  • R11.5: Data files will be named in conformance with C37.232, IEEE Standard for Common Format for Naming Time Sequence Data Files (COMNAME), revision C37.232-2011 or later
  • M11: Each GO has evidence that data was submitted in accordance with R11. Evidence may include but is not limited to (1) dated transmittals to the requesting entity with formatted records, (2) documents describing data storage capability, device specification, configuration or settings or (3) actual data recordings.
  • R12: Each GO shall within 90 calendar days of the discovery of a failure of the recording capability for the SER, FR or DDR data, either (1) restore the recording capability or (2) submit a Corrective Action Plan (CAP) to the Regional Entity and implement it.
  • M12: Each GO has dated evidence that meets R12. Evidence may include but is not limited to (1) dated reports of discovery of a failure, (2) documentation noting the date the data recording was restored, (3) SCADA records or (4) dated CAP transmittals to the Regional Entity and evidence that it implemented the CAP.
  • R13: Each GO shall:
  • R13.1: within three (3) calendar years of completing re-evaluation or receiving notification under R1.3, have SER or FR data as applicable for BES elements directly connected to the identified buses.
  • R13.2: Within three (3) calendar years of receiving notification under R5.4 have DDR data for elements identified during the re-evaluation.
  • M13: Each GO has dated evidence that meets R13. Evidence may include but is not limited to letters, emails, drawings or settings files.
  • C1.2:
  • GO shall retain evidence of R7, M7 for three (3) calendar years.
  • GO shall retain evidence of requested data provided as per R2, R3, R4, R8, R9, R10, R11 and R12, M2, M3, M4, M8, M9, M10, M11, and M12 for three (3) calendar years.
  • GO shall retain evidence of R13, M13 for five (5) calendar years.
  • If GO is found non-compliant, it shall keep information related to the non-compliance until mitigation is completed and approved or for the time specified above, whichever is longer.

Violation Severity Levels: R2, R3, R4, R7, R8, R9

  • Lower: 81-99% of required data
  • Moderate: 71-80% of required data
  • High: 61-70% of required data
  • Severe: 60% or less of required data

Violation Severity Levels: R10

  • Lower: 91-99% of required time synchronization data for R1 and R5
  • Moderate: 81-90% of required time synchronization data for R1 and R5
  • High: 71-80% of required time synchronization data for R1 and R5
  • Severe: <70% of required time synchronization data for R1 and R5

Violation Severity Levels: R11

  • Lower: 30-40 calendar days or 91-99% of required data or 91-99% of required data in the proper format
  • Moderate: 40-50 calendar days or 81-90% of required data or 81-90% of required data in the proper format
  • High: 50-60 calendar days or 71-80% of required data or 71-80% of required data in the proper format
  • Severe: > 60 days or <70% of required data or <70% of the required data in the proper format

Violation Severity Levels: R12

  • Lower: submitted CAP 91-100 calendar days after discovery of the failure
  • Moderate: 101-110 calendar days after discovery of the failure
  • High: 111-120 calendar days after discovery of the failure or GO submitted a CAP but failed to implement it
  • Severe: >120 calendar days after discovery of the failure or failed to restore the recording capability and failed to submit a CAP

Violation Severity Levels: R13

  • Lower: None
  • Moderate: late by 6 months or less for either R1.3 or R5.4
  • High: late by 6-12 months for either R1.3 or R5.4
  • Severe: late by >12 months for either R1.3 or R5.4

Look Ahead: PRC-002-5 was filed with the FERC on November 4, 2024 and will replace PRC-002-4 if and when approved.

Look Ahead Source: https://www.nerc.com/pa/Stand/Reliability%20Standards/PRC-002-5.pdf

Look Ahead Description: Changes from PRC-002-4 include:

  • R11.4: FR data will be provided either in CSV format with appropriate headers or in electronic files that are formatted in conformance with C37.111, (IEEE Standard Common Format for Transient Data Exchange (COMTRADE), revision C37.111-1999 or later
  • R11.5: DDR data will be provided either in CSV format with appropriate headers or in electronic files that are formatted in conformance with C37.111, (IEEE Standard Common Format for Transient Data Exchange (COMTRADE), revision C37.111-1999 or later
  • Violation Severity Level - R11: Lower: 1-10 calendar days or 91-99% of required data or 91-99% of required data in the proper format, Moderate: 11-20 calendar days or 81-90% of required data or 81-90% of required data in the proper format, High: 21-30 calendar days or 71-80% of required data or 71-80% of required data in the proper format, Severe: > 30 days or <70% of required data or <70% of the required data in the proper format

Links: https://www.nerc.com/pa/Stand/Reliability%20Standards/PRC-002-5.pdf

PRC-004-6 – Protection System Misoperation, Identification and Correction

Content unavailable at this time

PRC-005-1.1b – Transmission and Generation Protection System Maintenance and Testing

Content unavailable at this time

PRC-005-6 – Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance

Content unavailable at this time

PRC-006-5 – Automatic Underfrequency Load Shedding

Content unavailable at this time

PRC-006-NPCC-2 – Automatic Underfrequency Load Shedding

Content unavailable at this time

PRC-006-SERC-03 – Automatic Underfrequency Load Shedding Requirements

Content unavailable at this time

PRC-019-2 – Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection

Content unavailable at this time

PRC-023-6 – Transmission Relay Loadability

Content unavailable at this time

PRC-024-3 – Frequency and Voltage Protection Settings

Content unavailable at this time

PRC-025-2 – Generator Relay Loadability

Content unavailable at this time

PRC-026-2 – Relay Performance During Stable Power Swings

Content unavailable at this time

PRC-027-1 – Coordination of Protection Systems for Performance During Faults

Content unavailable at this time

PRC-028-1 – Disturbance Monitoring and Reporting Requirements for Inverter-Based Resources

Content unavailable at this time

PRC-029-1 – Frequency and Voltage Ride-Through Requirements for Inverter-Based Resources

Content unavailable at this time

PRC-030-1 – Unexpected Inverter-Based Resource Event Mitigation

Content unavailable at this time

VAR

VAR-001-5 – Voltage and Reactive Control

Content unavailable at this time

VAR-002-4.1 – Generator Operation for Maintaining Network Voltage Schedules

Content unavailable at this time

VAR-501-WECC-4 – Power System Stabilizer (PSS)

Content unavailable at this time

CIP

CIP-002-5.1a – Cyber Security – BES Cyber System Categorization

Content unavailable at this time

CIP-002-7 – Cyber Security – BES Cyber System Categorization

Content unavailable at this time

CIP-003-10 – Cyber Security – Security Management Controls

Content unavailable at this time

CIP-003-8 – Cyber Security – Security Management Controls

Content unavailable at this time

CIP-003-9 – Cyber Security – Security Management Controls

Content unavailable at this time

CIP-004-7 – Cyber Security – Personnel & Training

Content unavailable at this time

CIP-004-8 – Cyber Security – Personnel & Training

Content unavailable at this time

CIP-005-7 – Cyber Security – Electronic Security Perimeter(s)

Content unavailable at this time

CIP-005-8 – Cyber Security – Electronic Security Perimeter(s)

Content unavailable at this time

CIP-006-6 – Cyber Security – Physical Security of BES Cyber Systems

Content unavailable at this time

CIP-006-7 – Cyber Security – Physical Security of BES Cyber Systems

Content unavailable at this time

CIP-007-6 – Cyber Security – System Security Management

Content unavailable at this time

CIP-007-7 – Cyber Security – System Security Management

Content unavailable at this time

CIP-008-6 – Cyber Security – Incident Reporting and Response Planning

Content unavailable at this time

CIP-008-7 – Cyber Security – Incident Reporting and Response Planning

Content unavailable at this time

CIP-009-6 – Cyber Security – Recovery Plans for BES Cyber Systems

Content unavailable at this time

CIP-009-7 – Cyber Security – Recovery Plans for BES Cyber Systems

Content unavailable at this time

CIP-010-4 – Cyber Security – Configuration Change Management and Vulnerability Assessments

Content unavailable at this time

CIP-010-5 – Cyber Security – Configuration Change Management and Vulnerability Assessments

Content unavailable at this time

CIP-011-3 – Cyber Security – Information Protection

Content unavailable at this time

CIP-011-4 – Cyber Security – Information Protection

Content unavailable at this time

CIP-012-1 – Cyber Security – Communications between Control Centers

Content unavailable at this time

CIP-012-2 – Cyber Security – Communications between Control Centers

Content unavailable at this time

CIP-013-2 – Cyber Security – Supply Chain Risk Management

Content unavailable at this time

CIP-013-3 – Cyber Security – Supply Chain Risk Management

Content unavailable at this time

CIP-014-3 – Physical Security

Content unavailable at this time

CIP-015-1 – Cyber Security – Internal Network Security Monitoring

Content unavailable at this time

COM

COM-001-3 – Communications

Content unavailable at this time

COM-002-4 – Operating Personnel Communications Protocols

Content unavailable at this time

EOP

EOP-004-4 – Event Reporting

Content unavailable at this time

EOP-005-3 – System Restoration from Black Start Resources

Content unavailable at this time

EOP-006-3 – System Restoration Coordination

Content unavailable at this time

EOP-012-2 – Extreme Cold Weather Preparedness and Operations

Content unavailable at this time

IRO

IRO-001-4 – Reliability Coordination - Responsibilities

Content unavailable at this time

IRO-010-4 – Reliability Coordinator Data Specification and Collection

Content unavailable at this time

IRO-010-5 – Reliability Coordinator Data and Information Specification and Collection

Content unavailable at this time

MOD

MOD-025-2 – Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability

Content unavailable at this time

MOD-026-1 – Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Controls Functions

Content unavailable at this time

MOD-027-1 – Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions

Content unavailable at this time

MOD-032-1 – Data for Power System Modeling and Analysis

Content unavailable at this time

MOD-033-2 – Steady-State and Dynamic Model Validation

Content unavailable at this time

This site demo is unavailable on mobile devices.
Please come back on your computer.